/60
3
CPE - close report window

Report a question

You cannot submit an empty report. Please add some details.
CPE - tail spin

 

 

 

 


Florida General Project Management Exam - PRIVATE

Ready to take the next step toward becoming a licensed General Contractor in Florida? Your journey to success starts here! This is a free test that you can dive into a comprehensive 3-hour, 60-question practice test designed specifically for the Florida General Project Management Exam. This timed test is your perfect opportunity to sharpen your skills, identify areas for improvement, and build the confidence you need to ace the real exam.

Your Florida General Project Management Practice Exam

Ready to demonstrate your project management expertise? As a valued member, you've unlocked access to this comprehensive practice environment that mirrors the actual certification exam experience.

Your Exclusive Practice Session:

Drawing from our robust bank of over 180 professionally crafted questions, this free practice exam challenges you with 60 carefully selected questions in a 180-minute timeframe. This is your opportunity to experience the real exam format in a pressure-free environment.

Strategic Success Tip:

Maximize your performance using our bookmark feature. When you encounter a complex question, flag it and continue – this time-tested approach helps you maintain momentum and optimize your score. You can return to challenging questions once you've tackled the more straightforward ones.

What Makes This Practice Test Valuable:

Questions drawn from our extensive 180+ question bank

Full 180-minute time frame matches actual exam conditions

Professional-grade questions cover all key project management domains

Bookmark feature helps you develop effective test-taking strategies

Detailed feedback helps identify your strengths and areas for improvement

Ready to assess your project management knowledge? Click "Start" below to begin your practice exam.

Remember: This is your opportunity to gauge your readiness in a realistic testing environment. Let's make it count!

 

Please enter the password you were given.  
CPE - quiz maker eye visibility offCPE - quiz maker eye visibility

The number of attempts remaining is 3

Please enter your following information to get started:

 

1 / 60

CPE - bookmark empty

AN otice of Termination, of the Notice of Commencement may be executed by an owner that contains all of the following except _______.

2 / 60

CPE - bookmark empty

What is the MINIMUM thickness of exterior poured concrete basement and foundation walls with a MAXIMUM height of 8 feet and assigned to Seismic Design Category D or E?

3 / 60

CPE - bookmark empty

A contractor recognized there was a mistake in the contract documents regarding a construction activity and did not report it to the architect. The contractor performed the work anyway, knowing there was a mistake. Who shall bear the costs for correcting the mistake?

4 / 60

CPE - bookmark empty

A contractor is bidding on a project for a 11,250 square foot for a one-story complex 2,000,000 dollars is the amount available for this project at and the slab is 6" tick. The contactor wants to make 20% to 27% profit after paying the subcontractors for the project. Three sub-contractors send their bids to the prime contractor. Sub 1- wants 10% for shell, 5% for mechanical, 10% for electrical, 8 % for framing, 5% for finishes, 3% for window, 10% for roofing, 7% for parking 10% slab. Plus, 7% percent for taxes Sub 2- send the bid out for 65% for all respective trades plus 68,212.5 for the slab tax already added. Sub 3- send out a bid for 74.75% for the whole project tax included plus 12% mark up on money he saved the contractor.

Considering the above information, if each truck contains 10 cubic yard of concrete, each at $3000 per cubic yard, how many trucks of concrete is needed for the project? No waste factor.

5 / 60

CPE - bookmark empty

If an easement is to be secured for construction access, according to AIA 201, the __________secures and pays for it.

6 / 60

CPE - bookmark empty

A _____________ Group occupancy is the general classification for miscellaneous and utility structures.

7 / 60

CPE - bookmark empty

Buildings containing materials that present a detonation hazard are typically considered _______ occupancies.

8 / 60

CPE - bookmark empty

All masonry walls over ____ feet in height shall be adequately braced.

9 / 60

CPE - bookmark empty

A retention pond must be dug in Class "B" soil determined by thumb penetration test.  The retention pond will be 10 feet deep and measure 64 feet by 32 feet. The total cubic yards of dirt to be removed is ________. Do not consider the 25% fluff factor for the excavation.

10 / 60

CPE - bookmark empty

Any factory-built chimney used for a medium-heat appliance that produces flue gases with a temperature in excess of ______ °F is required to comply with UL 959.

11 / 60

CPE - bookmark empty

According to OSHA prior to excavation the contractor shall locate which of the following?

12 / 60

CPE - bookmark empty

Which of the following is a mistake that the estimator for a construction company should not make when estimating a project?

13 / 60

CPE - bookmark empty

__________is the term for the marker that establishes the boundaries of the lot for a building to be constructed.

14 / 60

CPE - bookmark empty

According to OSHA which choice would make the following statement false. The contractor must provide a ___________when working over or near water.

15 / 60

CPE - bookmark empty

A commercial cooking fire extinguishing system shall have a manual actuation switch located not more than what?

16 / 60

CPE - bookmark empty

When laying out batter boards for an excavation, they should be set back _______ from the edge of the excavation.

17 / 60

CPE - bookmark empty

________ is not a factor that influences the lateral concrete pressure on formwork.

18 / 60

CPE - bookmark empty

Open web steel joists must be manufactured to specifications from the Steel Joist Institute. Which of the following is NOT a specification from SJI?

19 / 60

CPE - bookmark empty

A Notice of Commencement must be filed in the clerk's office, which of the following may file it if there is no construction loan?

20 / 60

CPE - bookmark empty

Which of the following buildings would be classified as an A-2 occupancy?

21 / 60

CPE - bookmark empty

Pool lifts shall be located where the water level does not exceed _________  inches.

22 / 60

CPE - bookmark empty

The maximum noise level, beyond which the employee shall be provided protection, over a 4-hour period is:

23 / 60

CPE - bookmark empty

During construction the ____ will provide the administration of the contract as described in the contract documents and will be the owner's representative.

24 / 60

CPE - bookmark empty

A subcontractor's work is substantially complete and in accordance with the requirements of the prime contract. The contractor received application for payment from the subcontractor and made prompt application for payment to the architect for such work. The architect issued application for payment covering such work. According to AIA Document A401, the contractor shall pay the subcontractor within ____ days after the issuance of the certificate for payment by the architect.

 

 

25 / 60

CPE - bookmark empty

Lifting inserts, which are imbedded or otherwise attached to a precast member other than tilt-up member, shall be capable of supporting at least _______ times the maximum load.

26 / 60

CPE - bookmark empty

The building permit, or a copy of the permit, shall be kept ______ until completion of the project.

27 / 60

CPE - bookmark empty

Who is responsible for assuring that the work is accessible and exposed for inspection purposes?

28 / 60

CPE - bookmark empty

What is the maximum slope for a type B soil for an excavation less than 20' in depth?

29 / 60

CPE - bookmark empty

For a wire core manila rope that is to be used as a lifeline that might be subjected to cutting or abrasion, what is required minimum size of the rope?

30 / 60

CPE - bookmark empty

The outer jacket of a flexible duct section _________ be interposed between the flange of the duct collar fitting and the flexible duct.

31 / 60

CPE - bookmark empty

When debris is dropped through holes, in the floor without the use of chutes, the area onto which the material is dropped shall be enclosed with barricades.

32 / 60

CPE - bookmark empty

If the new occupancy is a food -handling establishment, all existing sanitary waste lines above the food or drink preparation or storage area shall be protected to prevent which of the following?

33 / 60

CPE - bookmark empty

Location of floor furnaces shall conform to which of the following requirements?

34 / 60

CPE - bookmark empty

Permanent Bottom Chord lateral restraint shall be installed as a continuous row spaced no more than ____________ or less if required but Truss design or building designer.

35 / 60

CPE - bookmark empty

Your job calls for you to excavate a perimeter trench around a poll area that is 3' wide and x 4' deep and runs 160 lineal feet. The soil is comprised of heavy soil and clay. You have no option but to excavate this trench by hand and you only have 1 day to get this accomplished. If the 160- foot trench forms a 50' x 30' rectangle, what is the area inside the rectangle?

36 / 60

CPE - bookmark empty

All excavations more than 8 feet but not more than 12 feet in depth which unsupported vertically sided lower portions shall have a maximum allowable slope of 1:1 and a __________________. OSHA subpart P Appendix.

37 / 60

CPE - bookmark empty

Use of a domestic open-top broiler unit requires a metal exhaust hood with which of the following characteristics?

38 / 60

CPE - bookmark empty

Which types of employers do not have an obligation to maintain OSHA records?

39 / 60

CPE - bookmark empty

The compressed air shall not be used for cleaning purposes except where reduce to less than how many P.S.I?

40 / 60

CPE - bookmark empty

Who's responsible for providing surveys describing physical characteristics, legal limitations, and utility locations for the site of a project? I chose (owner) AIA.

41 / 60

CPE - bookmark empty

The subcontractor may terminate the subcontract for nonpayment after how many days?

42 / 60

CPE - bookmark empty

What does AFUE stand for?

43 / 60

CPE - bookmark empty

A construction job will require a trench for PVC pipe 3' wide, 3' deep and 250yards long. Because of accessibility issues, the trench must be hand excavated. The soil is sandy loam. The job must be completed in 2 regular workdays (8 hours per person per day). The labor cost, per man, per whole day, is $110. The trench, by municipal code, must have yellow florescent tape around the entire perimeter of
the trench after normal working hours. How many feet of tape will be required for the perimeter of the trench?

44 / 60

CPE - bookmark empty

According to the AIA document requirements, a change order must be signed by which of the following:

45 / 60

CPE - bookmark empty

A contractor is going to set a 70' long wood truss. According to BCSI, it must be picked with a strongback attached to the top chord and web members at intervals of approximately __________.

46 / 60

CPE - bookmark empty

The approximate out-of-plane tolerance for a 20'long truss is _______.

47 / 60

CPE - bookmark empty

If a contractor receives a $10,000 initial payment on a contract with a value of $100,000, he must apply for the permit for the project within _______ days.

48 / 60

CPE - bookmark empty

If there is conflict in the code between a general requirement and a specific requirement, the ____________ requirement shall apply.

49 / 60

CPE - bookmark empty

According to BCSI, for lifting truss spans in excess of 60 feet, a "Stiffback" should be attached to the top chord and web members at approximate __________ foot intervals.

50 / 60

CPE - bookmark empty

Interior spaces intended for human occupancy shall have a heating system capable of maintaining what level of temperature measured 3 feet off the floor?

51 / 60

CPE - bookmark empty

Long length Continuous top chord temporary lateral restraints shall have diagonal braces at maximum of how many feet?

52 / 60

CPE - bookmark empty

A contractor is bidding on a project for a 11,250 square foot for a one-story complex 2,000,000 dollars is the amount available for this project at and the slab is 6" tick. The contactor wants to make 20% to 27% profit after paying the subcontractors for the project. Three sub-contractors send their bids to the prime contractor. Sub 1- wants 10% for shell, 5% for mechanical, 10% for electrical, 8 % for framing, 5% for finishes, 3% for window, 10% for roofing, 7% for parking 10% slab. Plus, 7% percent for taxes Sub 2- send the bid out for 65% for all respective trades plus 68,212.5 for the slab tax already added. Sub 3- send out a bid for 74.75% for the whole project tax included plus 12% mark up on money he saved the contractor.

How many cubic yards of concrete will the subcontractor order for poor the slab if considered a 2% waste factor?

53 / 60

CPE - bookmark empty

For a 40' span scissor truss with 5/12 slope and a pitch difference of 3, would require top chord lateral bracing spaced at _____.

54 / 60

CPE - bookmark empty

Which is NOT a delay factor when determining production efficiency percentages?

55 / 60

CPE - bookmark empty

If there is conflict in the code between a general requirement and a specific requirement, the ______ requirement shall apply.

56 / 60

CPE - bookmark empty

When a pedestrian barrier is required at a construction site, what is the MINIMUM height that the barrier shall be built extending the entire length of the site?

57 / 60

CPE - bookmark empty

A contractor is bidding on a project for a 11,250 square foot for a one-story complex 2,000,000 dollars is the amount available for this project at and the slab is 6" tick. The contactor wants to make 20% to 27% profit after paying the subcontractors for the project. Three sub-contractors send their bids to the prime contractor. Sub 1- wants 10% for shell, 5% for mechanical, 10% for electrical, 8 % for framing, 5% for finishes, 3% for window, 10% for roofing, 7% for parking 10% slab. Plus, 7% percent for taxes Sub 2- send the bid out for 65% for all respective trades plus 68,212.5 for the slab tax already added. Sub 3- send out a bid for 74.75% for the whole project tax included plus 12% mark up on money he saved the contractor.

How much money will the contractor have to pay if he hires subcontractor 1?

58 / 60

CPE - bookmark empty

A fully planked or decked floor or nets shall be maintained within two stories or _____ feet whichever is less , directly under any erection work being performed.

59 / 60

CPE - bookmark empty

The ____ shall be exclusively accountable for and have control over construction means, methods, techniques, sequences and procedures, and for coordinating all portions of the work under the contract.

60 / 60

CPE - bookmark empty

A construction job will require a trench for PVC pipe 3' wide, 3' deep and 250yards long. Because of accessibility issues, the trench must be hand excavated. The soil is sandy loam. The job must be completed in 2 regular workdays (8 hours per person per day). The labor cost, per man, per whole day, is $110. The trench, by municipal code, must have yellow florescent tape around the entire perimeter of
the trench after normal working hours.
How many laborers will be needed to complete the job within the required time?

Your score is

The average score is 81%

0%